Equipment component(one machine) |
l Double head 3 Tons Manual de-coiler*1 l Feeding guide system*2 l Mainly forming system(Chian driven)*2 l Hydraulic cutting system(Track cutting) *2 l Hydraulic station*2 l PLC Control system *2 l Run out table*2 |
Material |
Thickness: 0.3-0.8mm Material: GI, GL. |
Power supply |
380V, 50Hz, 3 phase(Or customized) |
Capacity of power |
Roll forming machine main power: 5.5kw*2 Servor motor: 2.2kw*2; hydraulic: 3.0kw*2; |
Speed |
Line speed: 40m/min |
Dimension |
Approx.(L*W*H) 5m*1.5m*1.3m (one machine) Total length:10-12 meters include the decoiler and receiving table. |
Stands of rollers |
Usually Furring 12 rollers; L angel 9 rollers |
For the forming part:
Main power: |
5.5kw |
Panel: |
Torrist stand structure |
Forming speed: |
Speed is 40m/min, |
Shaft material and diameters: |
Shaft material and diameters: #45 steel and 50mm
|
Roller material: |
Cr12 with well heat treatment ,58-62 |
Forming Steps: |
Furring 12 rollers; L angel 9 rollers |
Driven: |
Chain driven |
Cutting: |
No stop cutting |
Voltage: |
380V 50HZ 3Phases |